Bruce Unit 2 Lay-Up Engineering Assessment
Main Article Content
Abstract
The overall lay-up program initiated as a result of the strategic decision to shut down Bruce A unit 2 is briefly described as an introduction to the engineering assessment of the unit 2 systems. The assessment has identified the need to prepare 67 system and 9 equipment lay-up specifications. A summary of the selected system specifications is described. A complete summary and the specifications and the status of unit 2 systems and equipment required to support lay-up and/or the other three operating units is avail- able on request due to the volume of the information. Some logistical details of the lay-up implementation plans, results, and problems to date demonstrate the complexity of the lay-up requirements for a nuclear unit in a multi-unit CANDU station.