The paper presents an overview regarding current and future activities related to the management of safety and regulatory framework at the Gentilly-2 Nuclear Generating Station. The paper discusses alignment of these activities with the best Canadian and international practices. It also proposes manners to develop a consistent risk-informed safety management system. The paper takes particularly into consideration the impact of this new framework on the refurbishment project, and the operations after the refurbishment of the station.