Development of a Risk-Informed Safety Management System at The Gentilly-2 Nuclear Generating Station
Main Article Content
Abstract
The paper presents an overview regarding current and future activities related to the management of safety and regulatory framework at the Gentilly-2 Nuclear Generating Station. The paper discusses alignment of these activities with the best Canadian and international practices. It also proposes manners to develop a consistent risk-informed safety management system. The paper takes particularly into consideration the impact of this new framework on the refurbishment project, and the operations after the refurbishment of the station.
Article Details
Section
Articles