Environmental Assessment: Challenges and Opportunities
Main Article Content
Abstract
As part of a $4.5 billion investment, Bruce Power is refurbishing Bruce A Units 1 and 2, having successfully completed an environmental assessment to return these units to service after a layup of almost 10 years. The project includes implementing a series of refurbishments and upgrades which will enhance safety, increase electricity generation capacity and improve reliability for the 30-year extended life of the units. This paper describes four challenges that were successfully managed during the extensive environmental assessment: (i) defining the scope of the Project; (ii) understanding the EA trigger under the Canadian Environmental Assessment Act; (iii) maintaining an effective relationship with the regulatory agencies; and (iv) managing stakeholder communications.