Abstract

The process development test program for production of Slightly Enriched Uranium (SEU)



dioxide powder and Blend of Dysprosium and Uranium (BDU) oxide powder was initiated



almost simultaneously with the conceptual engineering study for the commercial plant in 2001. During the very early phases of the project it was recognized that meeting the challenging requirements would necessitate wide expertise from different departments within the Cameco operations as well as consultants from outside the Company. The project team formed reflected this recognition. The conceptual engineering study was the lead into preparation of the engineering design study in 2003, which provided the process description based on the research and development program being carried out at Cameco Technology Development (CTD), project description, and project cost estimates. The detailed engineering phase commenced in June 2004 and was in progress at the the time when this paper was presented. The detailed engineering phase is addressing all aspects of the commercial plant including all health and safety, environment and security related issues, nuclear safety, training program, all product quality assurance issues, quality management issues, powder and fuel bundle transportation issues, all regulatory requirements, establishing project execution plans and budget, and strategies to control the costs. At the end of the detailed engineering phase, construction packages will be ready for tender, and major pieces of equipment will be selected and procured.

Article Details

Section
Articles