Pickering Irradiated Fuel Transfer Conveyor Isolation
Main Article Content
Abstract
Pickering A NGS has been in operation for 25 years and is one of the longest in service CANDU stations. Some underwater fuel handling equipment, notably the conveyor stops, have been without maintenance throughout that time. This paper describes the concept of a conveyor isolation system that permits draining of a single or multiple elevator columns and also the early stages of a development program for the elastomeric sealing element. The prototype seal element has been proven in lab tests to be capable of limiting leakage to 0.5 IGPM at the design pressure of 6.5 psi. The design of a sealing element is particularly interesting because the conveyor tube is a square cross-section which contains an additional obstruction, a conveyor drive cable. A seal delivery, actuating and positioning system has been conceptually laid out and the design is proceeding with projected implementation in 1998.
Article Details
Section
Articles